Tuesday, 6 November 2018

draft daily activity

Dear Team,

berikut coba kami buatkan draft daily activity report, agar kedepannya kegiatan teman-teman bisa tetap di record dan meminimalisir miss yang terjadi.

berikut draft yang kami butuhkan, silahkan coppas dan di buat acuan untuk report selanjutnya.

========================================================
Nama: "nama saya"
Bagian Pekerjaan: "PC / QC / ME / FS / HSE

1. Tool Box Meeting Internal

2. Site Visit :
- Survey Lapangan Premium, ADO & RFO (PAFT)
- Material Dimensional

#ADO : Mechanical Job
* Annular Plate :
- Laying ....%
- Fit-Up ....%
- Welding ....%
* Bottom Plate
- Laying ....%
- Fit-Up 7...%
- Welding .....% ; SMAW (Root) 16 weld ; Complete Weld with SAW 21 weld ; Complete Weld with SMAW 43 weld
* Shell Plate Course 6
- Fit-Up 70-75%

* Civil : Pipe Slipper job (Pengecoran 9 from 33) ; Fabrication tail banwall


#Premium : Asphalt 100%
- Penimbun / pemadatan tanah di samping beton Tangki
- Install Tirai air


#RFO : Asphalt 100%
- Penimbun tanah di samping beton Tangki


3. Reporting

========================================================